Parallel Machine Scheduling
We assume
1. Total Completion Time
SPT can be generalized to
WSPT approximates
2. Makespan
With
I.e. the makespan is at least the maximum processing time of a job, and at least the average load across all machines.
To solve
- Schedule an arbitrary job on macinne 1 at time 0.
- Start any unscheduled job as soon as possible on the same machine.
- Repeat until the makespan on the machine exceeds
or all jobs have been scheduled. - If the makespan exceeds
, preempt the last job and continue scheduling on the next machine.
The non-preemptive case is NP-hard even on
PROOF (Examinable)
- If job
finishes last, it started at . - Since machines are always busy before
, the work completed is at least . - Hence,
. - Plugging in
gives . - For any makespan, including the optimal,
. - Hence,
and . - Hence,
. So,
.
2.1 LPT Scheduling
List Scheduling is
3. Summary
| Problem | Complexity | Optimal Policy |
|---|---|---|
| P | McNaughton (wrap-around) | |
| P | SPT | |
| NP-hard | WSPT ( | |
| NP-hard | LPT ( |